Power
Project: | DUBAL Substation upgrade |
End User: | DUBAL |
Status: | Completed |
Process of Implementation
Dubai Aluminium (“DUBAL”) operates one of the world’s largest single site aluminium smelters – hot metal production and was the second highest in the global alumimium industry
Working on a large scale process control project at Dubal allowed the enhancing of our technical expertise and development of our core strengths
The project scope mainly included Design, Assembly, Testing and Commissioning of complete range of LV switchgear panels (Intelligent motor control centers) for the sub-station DESAL, Cast House, Potline and Dockship unloader which contains the implementation of special control functions for furnace door drives, cooler door drives, dockship unloader with crane controls etc.
Binghalib Engineering implemented arc falut protection relay for low voltage systems (Motor Control Centers) which is one of the first kinds in UAE, installation of which will detect art fault in any compartment / busbar chamber, cable chamber
Panels were incorporated with device net and Ethernet for high speed communication, special protection functions & relays have been incorporated exclusively to to comply latest requirements. For example, event recorded type relays for monitoring systems etc.
Follow us:
Related Projects
Power
AL LAYYAH POWER PLANT End User: SEWA → Contractor: Alsewedy Electric → Channel partners: ABB / Logstrup JEBEL ALI STATION M End User: DEWA → Consultant: Fitchner → Contractor: Foosan → Channel partners: Schneider Electric JADA SUBSTATION End User: SEWA → Channel partners: ABB / Logstrup PRS SUBSTATION End User: SEWA → Channel partners: ABB […]
AL LAYYAH POWER PLANT
End User: SEWA → Contractor: Alsewedy Electric → Channel partners: ABB / Logstrup
JEBEL ALI STATION M
End User: DEWA → Consultant: Fitchner → Contractor: Foosan → Channel partners: Schneider Electric
JADA SUBSTATION
End User: SEWA → Channel partners: ABB / Logstrup
PRS SUBSTATION
End User: SEWA → Channel partners: ABB / Logstrup
WASIT SUBSTATION
End User: SEWA → Channel partners: ABB / Logstrup
DEWA PH3 800MW SOLAR PLANT
End User: DEWA / MASDAR → Consultant: GRS / iLF Consultants → Contractor: DANWAY → Channel partners: Schneider / BlokSeT
Power
Project: DUBAL Substation upgrade End User: DUBAL Date: June, 2014 Status: Completed Process of Implementation Dubai Aluminium (“DUBAL”) operates one of the world’s largest single site aluminium smelters – hot metal production and was the second highest in the global alumimium industry Working on a large scale process control project at Dubal allowed the enhancing […]